The question often thrown on the table is to whom should management listen? How can management be sure they are getting the right information? There is no certain answer to this, but a discerning manager can listen to everyone on duty and identify the real substance. When everyone sings in chorus and one does not, it does not mean he is wrong. Continue reading

Advertisements
Posted in Baseline Management, Book, Business, Decision Making, Issues and Problems, risk, Risk Assessment and Treatment, Risk Relativity, Risk Universe, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats, Tools, Uncategorized | Tagged , , , , , , , , , , | Leave a comment

Project Schedule Baseline Top Ten Prerequisites

Baseline prerequisites:
1. The baseline schedule shall represent the most likely schedule

The baseline schedule is the most-likely schedule. It does not have built-in float, buffer duration, or/and dummy activities. It is neither optimistic nor pessimistic (tight or lax).

Reminder:

It has full complement of qualified resources, with no embedded risk or any built-in schedule contingency.

2. An official project BL Schedule shall be a result of Interactive Planning

All baselines set from Gate 2 onward shall be the result of an interactive planning session.

3. Schedule scope shall equal plan scope

The plan scope shall be the same scope reflected in the baseline schedule that follows. Planned scope and the scheduled scope must be in alignment. A schedule cannot have more than the scope in the plan. Otherwise, the project faces a problem (Frago, Schedule Baseline Dilemma Part 1, 2015).

Read the whole article for complete list! Continue reading

Posted in Analysis, Baseline Management, Business, Causes and effects, Construction Management, Data Assessment, Data Maturity, earned value, Execution Strategy, Information Maturity, Integrated Schedule, Integration, Issues and Problems, Managing Assumptions, Planning and Scheduling, Primavera Administration, Program Management, Program Schedule, Progress Measurement, Project Management, Quality Management, Risk Assessment and Treatment, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats, Tools, Type of Analysis, Uncategorized, Variance Analysis | Tagged , , , , , , , , , , , , , , , , | 1 Comment

Setting the Critical Path

In the big situation, a man’s blind belief usually ends in disaster. Continue reading

Posted in Analysis, Business, Causes and effects, Construction Management, Critical Path, Critical Path Management, Data Assessment, Execution Strategy, Integrated Schedule, Integration, Longest Path, Opportunities, P6 Issues, Planning and Scheduling, Program Management, Program Schedule, Project Management, Quality Management, Reporting, Risk-based Management, rufran frago, Rufran's Blogs, Tools, Uncategorized, Variance Analysis | Tagged , , , , , , , , , , , , , , , , , , , , , | Leave a comment