Risk-based Planning and Scheduling Slides (SAIT Presentation)

101116 Risk-based Planning & Scheduling (My SAIT Slides) from RUFRAN FRAGO, P. Eng., PMPĀ®, CCP, RMPĀ®, Author Advertisements

Posted in Analysis, Baseline Management, Business, Causes and effects, Construction Management, Critical Path, Critical Path Management, Data Assessment, Data Maturity, Decision Making, Deterministic Schedule, E-Touch Up, E-Touch Up Products, Information Maturity, Integrated Schedule, Integration, Issues and Problems, Managing Constraints, Opportunities, Planning and Scheduling, Primavera Administration, Program Management, Program Schedule, Progress Measurement, Project Management, Risk Assessment and Treatment, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats | Tagged , , , , , , | Leave a comment

Project Schedule Baseline Top Ten Prerequisites

Baseline prerequisites:
1. The baseline schedule shall represent the most likely schedule

The baseline schedule is the most-likely schedule. It does not have built-in float, buffer duration, or/and dummy activities. It is neither optimistic nor pessimistic (tight or lax).

Reminder:

It has full complement of qualified resources, with no embedded risk or any built-in schedule contingency.

2. An official project BL Schedule shall be a result of Interactive Planning

All baselines set from Gate 2 onward shall be the result of an interactive planning session.

3. Schedule scope shall equal plan scope

The plan scope shall be the same scope reflected in the baseline schedule that follows. Planned scope and the scheduled scope must be in alignment. A schedule cannot have more than the scope in the plan. Otherwise, the project faces a problem (Frago, Schedule Baseline Dilemma Part 1, 2015).

Read the whole article for complete list! Continue reading

Posted in Analysis, Baseline Management, Business, Causes and effects, Construction Management, Data Assessment, Data Maturity, earned value, Execution Strategy, Information Maturity, Integrated Schedule, Integration, Issues and Problems, Managing Assumptions, Planning and Scheduling, Primavera Administration, Program Management, Program Schedule, Progress Measurement, Project Management, Quality Management, Risk Assessment and Treatment, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats, Tools, Type of Analysis, Uncategorized, Variance Analysis | Tagged , , , , , , , , , , , , , , , , | 1 Comment

Ten Cardinal Rules to Good Schedule BL Management

When client and contractor start throwing accusations against each other surrounding schedule baseline, one can easily conclude that a problem or issue is brewing. It can turn into big risks (Frago, Schedule Baseline Dilemma Part 1, 2015). Resolving the contentions between opposing parties can take long and potentially, can end in disaster.

To prevent such occurrence, the project must start with the right foot forward. The project manager, all his planners, and schedulers, including his contract administrators must have a solid understanding on how the project intends to manage schedule baselines.

If baseline management is not part of the plan, the project is trekking on dangerous territory. Continue reading

Posted in Analysis, Baseline Management, Business, Causes and effects, Construction Management, Integrated Schedule, Issues and Problems, Planning and Scheduling, Primavera Administration, Program Management, Program Schedule, Progress Measurement, Project Management, Risk Assessment and Treatment, rufran frago, Rufran's Blogs, Schedule Baseline, Threats, Uncategorized, Variance Analysis | Tagged , , , , , , , , , , , , , , | 1 Comment