Risk-based Management in the World of Threats and Opportunities: A Project Controls Perspective

Risk-based Management in the World of Threats and Opportunities: A Project Controls Perspective Continue reading

Posted in Analysis, Baseline Management, Black Swans, Book, Business, Causes and effects, Construction Management, Data Assessment, E-Touch Up, E-Touch Up Products, Opportunities, Opportunity, Project Management, Publication, Risk Relativity, Risk Universe, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats | Tagged , , , , , , , , , , , , | Leave a comment

Project Schedule Baseline Top Ten Prerequisites

Baseline prerequisites:
1. The baseline schedule shall represent the most likely schedule

The baseline schedule is the most-likely schedule. It does not have built-in float, buffer duration, or/and dummy activities. It is neither optimistic nor pessimistic (tight or lax).

Reminder:

It has full complement of qualified resources, with no embedded risk or any built-in schedule contingency.

2. An official project BL Schedule shall be a result of Interactive Planning

All baselines set from Gate 2 onward shall be the result of an interactive planning session.

3. Schedule scope shall equal plan scope

The plan scope shall be the same scope reflected in the baseline schedule that follows. Planned scope and the scheduled scope must be in alignment. A schedule cannot have more than the scope in the plan. Otherwise, the project faces a problem (Frago, Schedule Baseline Dilemma Part 1, 2015).

Read the whole article for complete list! Continue reading

Posted in Analysis, Baseline Management, Business, Causes and effects, Construction Management, Data Assessment, Data Maturity, earned value, Execution Strategy, Information Maturity, Integrated Schedule, Integration, Issues and Problems, Managing Assumptions, Planning and Scheduling, Primavera Administration, Program Management, Program Schedule, Progress Measurement, Project Management, Quality Management, Risk Assessment and Treatment, Risk-based Management, rufran frago, Rufran's Blogs, Schedule Baseline, Threats, Tools, Type of Analysis, Uncategorized, Variance Analysis | Tagged , , , , , , , , , , , , , , , , | 1 Comment