Egad! It is the Most Likely Schedule!

One has to remember that a schedule is a time estimate. It is not the exact actual time value at the time. Experienced professionals try to provide a plausible estimate. Nobody really knows what would be the definitive value.

ML date (or most likely duration) is not the same as expected date (or expected duration). It is but a component of the expected value. With the three point estimates (Triangular or Beta) available, one can calculate the expected duration of an activity, a group of activity, and the whole project’s duration.

It is one of the questions asked more often in risk-based planning and scheduling. Project directors, managers, planners, and schedulers have to know what this term means.

Each time a scheduler tries to explain the concept, he easily gets lost in his own circumlocution. It might be his indirectness compounded by the fact that this particular term shares common but blurred boundaries with some other project and risk management terms.

In view of such difficulties, let us put their words and thoughts on paper so that project practitioners can better understand. Continue reading

Posted in Analysis, Baseline Management, Business, Construction Management, Critical Path, Data Assessment, Decision Making, Deterministic Schedule, Economics, Integrated Schedule, Most Likely Schedule, Planning and Scheduling, Program Management, Program Schedule, Project Management, Risk Assessment and Treatment, Risk Universe, Risk-based Management, rufran frago, Rufran's Blogs | Tagged , , , , , , , , , , , , , , , , , , , | Leave a comment